Metropolitan Residences - Roof Covered

Austino Property Group is delighted to provide the latest update to you from Metropolitan residences.



Works continue to progress well despite the extreme weather over the past few months. The roof slab to the tower was poured in January this year.


Progress to commercial levels have continued with the block work to service rooms, amenity areas. The upper residential levels are also progressing well with services contractors reaching level 11. The finishing trades are progressing with the tiler and membrane contractor working on level 5 and facades contractors installing cladding and glazing on the lower levels.


The anticipated completion date for Metropolitan Residences will be in late year 2017.