Parkside Residences - Project Update

After finishing all the underground piling and drainage works for the entire project last year, construction of Stage 1 building commenced at the beginning of this year.

Despite having to endure 2 COVID-19 lockdowns, construction is progressing relatively smoothly, and everything is going well on the project.

All basement structural concrete works have been completed, and work is now progressing on the concrete superstructure.  The concrete floor slab to the ground floor has been completed, including all required under slab services. Precast concrete panels and all associated structural steelwork to both the ground and 1st floor have been erected, including the formation of the 1st floor suspended concrete floor slab.  The internal fit-out has just commenced to the 4 apartments located on the ground floor. Fit-out to level 1 will commence shortly.  

Over the coming months, the concrete superstructure will be completed with the roof structure being programmed to be in place by the end of this year.

© 2019 by Austino Property Group

  • Facebook - White Circle
  • Twitter - White Circle